April 6th 2007
Friday 10 am.
All containers have been delivered in Grubbenvorst.
April 5th 2007
What a week !!!
Customs on strike and a fight to get the containers in time in Grubbenvorst.
Yesterday the cleared 2 containers , but we could not find out which ones.
But today 5 minutes before closing time of the customs office they cleared all 4
containers?
So not tomorrow, but Saturday will be the unpacking day.
Pfffffffffffffffffffffffffffffff
April 1st 2007
The containers arrived on schedule today in
Rotterdam.
The are already unloaded and waiting for further processing.
If everything is going ok we will try to unpack all 4 on Friday !!!!!!. But I
will advise all the owners in time
by email.
The first thing Monday morning will be contacting the shipping company for
further details.
September 23rd 2006
Job done.
All 4 containers are packed and ready foir the trip down under.
On MOnday morning the containers will be transported to Rotterdam by truck and
from there
by ship to Melbourne.
We expect them to arrive in Corowa on the first of November.
September 16 th 2006
As scheduled, we packed Blue on Friday and Green on
Saturday.
With the help of good weather and , helpfulle pilots and all beeing on time in
Grubbenvorst
we were able to finish the containers on both days in the mid afternoon.
More see daily news.
August 17 th 2006
This morning we finished all the work with the
chamber of commerce and insurance.
Not easy this time as we have 24 gliders. We have to put some of the big ships
in
2 containers wings in one and fuselage in another one. But as mentioned all the
paperwork
has been done.
For the container packing, we made a 6m x 4m cover with frame just in case we
have some rain
during packing.
Sorry for the pilots who can't come with us this year. The containers are full
and we still
have 2 gliders waitlisted.
August 7 th 2006
A few weeks to go.
Everything is organized and we are looking foreward to meet everybody in
Grubbenvorst.
The container setting is final, though we might swap the big fuselages to other
containers.
At the moment all 4 containers are fully booked and 1 glider waitlisted.
July 28 th 2006
Time is going fast.
Today I finalized the container setting and packing dates.
July 4th th 2006
We made the final decision to go with 4 containers.
The container setting is not final as we have to puzzle which glider in which
container.
When ready I will change Provisional container
setting into Final container
setting
June 13 th 2006
The 4 containers are almost fully booked.
We are forced however to travel back to Australia early August, so there won't
be time
to build the 5th container (if needed) this year.
Don't worry we will be back in September to pack the containers.
Note: The provisional schedule is NOT your
final place in a container.
As soon as we know all the gliders we start puzzling to put all the gliders on
the right spot and
the setting will be published as Final
container setting and time schedule.
February 24th 2006
The first of April will be the day that we will open
the list for the transport of next season.
All the pilots who already send a request will have an email in the next week.
Due to the amount of enquiries at this stage we consider a 5th container for
Corowa.
Final Container setting and time schedule,
| Blue Container CPIU 99723 9 | Green Container CPIU 992140 0 | ||||
| TYPE OF GLIDER | CN | Status | TYPE OF GLIDER | CN | Status |
| DG 800 | ZY | ok | Ventus 2 cxt | LK | ok |
| Ventus 2 ct | AR | ok | Ventus 2 cxt | RA | ok |
| ASH 26E | 6E | ok | Discus 2 t | IZ | ok |
| Ventus 2 cm | NL | ok | Ventus ct | SY | ok |
| Ventus 2 cm | JM | ok | DG1000T | NIT | ok |
| Ventus b | AJ | ok | Ventus cm | ILH | ok |
| Red Container CPIU 999728 3 | White Container SNGU 4905822 | ||||
| TYPE OF GLIDER | CN | Status | TYPE OF GLIDER | CN | Status |
| Ventus 2 ct | PZ | ok | Duo Discus T | FOX | ok |
| ASH 26E | MK | ok | DG 808b | N | ok |
| Venus cm | HD | ok | Ventus 2 ct | JR | ok |
| DG 505 | DG | ok | Ventus 2 ct | CT | ok |
| Ventus cm | DS | ok | ASW27 b | 3W | ok |
| Ventus 2 ct | 11 | ok | Phonix | JAsh | ok |
Final Schedule
|
BRGWY
Estimated date |
Date done | Action | Container |
| 15-09-2006 Fri | Packing the container in Grubbenvorst | Blue | |
| 16-09-2006Sat | Packing the container in Grubbenvorst | Green | |
| 22-09-2006 Fri | Packing the container in Grubbenvorst | Red | |
| 23-09-2006 Sat | Packing the container in Grubbenvorst | White | |
| 25-09-2006 Mon | Containers leaving Grubbenvorst | BRGW | |
| 28-09-2006Thu | Leaving Rotterdam | BRGW | |
| 23-10-2006 Mon | Estimated arrival Melbourne | BRGW | |
| 01-11-2006 Wed | Estimated arrival Corowa | BRGW | |
| 03-11-2006 Fri | Estimated Quarantine Inspection | BRGW | |
| 04-11-2006 Sat | First possible flying day | BRGW | |
| 15-02-2007 Thu | Packing Corowa | BRGW | |
| 16-02-2007 Fri | Packing Corowa | BRGW | |
| 17-02-2007 Sat | Packing Corowa | BRGW | |
| 18-02-2007 Sun | Leaving Corowa | BRGW | |
| 22-02-2007Thur | leaving Melbourne | BRGW | |
| 02-04-2007 Mon | Estimated arrival Rotterdam | BRGW | |
| 06-04-2007 Fri | Estimated arrival Grubbenvorst | BRGW | |
| 06-04-2007 Fri afternoon | Unpacking the containers | BR | |
| 07-04-2007 Sat | Unpacking the containers | GW |